This research will be completed by the end of this month . Thus, MLTA will first idea on the journey to be made by light rail . It will submit the preliminary alignment Singaporeans for an initial assessment .
Subsequently, a "request for proposal " will be made by the MLTA six firms were selected for the project. These six firms are two companies from India , two from China, one from France and one from England. These companies will have time to evaluate the project and make their proposals.
Negotiations will then be undertaken with the top three of them. However, only one will be selected for the final contract to be signed by 31 October 2014.
The company that will stall the contract must provide the design, construction, financing , operation and will also be responsible for maintaining the light rail . Furthermore, the light rail does not travel the path of the highway, but happens in the cities , especially Curepipe, Vacoas, Rose Hill and Beau-Bassin . Then it will go to Coromandel and Great River Northwest to complete the trip to Port Louis.
It is also possible that there is an alignment between Bagatelle and Ebony to attract more passengers.
Regarding the car , it will be 45 meters long. It is also expected that there are five cars.
After 30 years of service, there will be a renegotiation between the consortium and the government in mind that the Government is responsible for the operation of the light rail .