Six months of work were needed on the road at Montagne-Ory, blocked following a landslide. And it's 15 o'clock this Sunday, September 22 it will be reopened to traffic.
A retaining wall including currently built to prevent a new landslide occurs at this location. The work was undertaken by the firm Colas. They cost around Rs 18 million.
Other road projects, meanwhile, still under construction across the island. Overview.
Road Terre Rouge-Verdun great strides
In November, motorists can take the road Terre Rouge-Verdun, according to a Department of Public Infrastructure. The work on this road, 15.7 km long, are about 90% completed and should be completed by the end of October.
The contractor is installing street lights and traffic signs and marking the road.
In fact, the entry into operation of the road has been delayed due to several landslides in the region of Revelry. Technicians had to make changes to the original plan.
M1 - Hillcrest Avenue: the project on track
It should be operational within two weeks. But the connection between the M1 and Hillcrest Avenue, Quatre-Bornes, was delayed. It will not open until December, according to the Minister of Public Infrastructure, Anil Bachoo. The reason: the work to replace the existing drains.
With this new route, motorists from Curepipe and the South will not have to go through the roundabout at St John then Tulip Avenue, Quatre-Bornes, to access the Hillcrest Avenue. A roundabout is also planned and will be the focal point between the opposite lane.
The Ring Road facing barriers
With the start of construction of the second phase of the Ring Road , many families will be relocated. Furthermore squatters Bangladesh, Tranquebar, other inhabitants of this region are affected. The house of Christian Bernard is one of four houses that the state will have to acquire as they are on the road. Located at the foot of Mount Thumb, this "castle" is estimated at Rs 16 million ... " I made a proposal to the government. I would like to know how I feel , "said Christian Bernard.
The second phase of the Ring Road to connect Sorèze Vallée Pitot and roundabout Quai-D. It will include a tunnel that crosses the mountain signals, connecting Guibies at Tranquebar and a circular route between Tranquebar and roundabout Caudan
As the first phase of the Ring Road , it was inaugurated in February after nearly three years of work. 4.5 km long, the new ring road at a cost of Rs 1.2 billion, extends from Sorèze Guibies.
Once the project is completed, motorists from the South will visit the North without going through the Place d'Armes and the center of the capital.